The Savannah Harbor Expansion Project gained more traction in March.

Several features are on schedule to be completed by the end of 2017, including the First Dike Raising (June); Raw Water Storage Impoundment (July); CSS Georgia Recovery (Sept.); Dissolved Oxygen Injection System (Dec.); and the Sediment Basin Tide Gate Removal (Dec.).

Entrance Channel Dredging, which is currently 53 percent complete, is expected to wrap up in July 2018.

Other features, such as McCoy’s Cut, the New Savannah Bluff Lock & Dam Fish Passage and Inner Harbor Dredging are still in the design phase.

Video produced by Jeremy S. Buddemeier, U.S. Army Corps of Engineers Savannah District. Additional footage courtesy of Georgia Ports Authority, Continental Heavy Civil and Thalle Construction. Music by thepassionhifi.com.


Member Comments…







Quick Links
Savannah - Tybee Island News
Savannah - Tybee Island Photos
Savannah - Tybee Island Videos




About Us
Contact Us
Site Map
Search Site
Advertise With Us
   
Savannah.USCoast.info
THE SAVANNAH - TYBEE ISLAND WEBSITE

Copyright 2024, Coastal Town
Privacy    |    Legal